- Current CIP Projects -
The Citizen Office serves to proactively minimize the effects of capital improvement projects in a defined geographic area by coordinating city services to meet the needs of citizens impacted by the projects.
Edgemere / Sackville Curb & Gutter Improvement Project
Description: This project includes new 8” water main with new laterals to each house; replacement and/or new fire hydrants; stormwater improvements; and new sidewalks, curbing, gutters, driveway aprons and parking bays along the following streets:
53rd between Live Oak and Ash Streets
54th between Live Oak and Ash Streets
55th between Waters Ave and Ash Streets
Contact: Heather Fish, Citizen Specialist, 651-6488
- Citizen Engagement & Other Projects -
Citizen Engagement describes any process that strives to inform, gather input or involve the public regarding decision-making processes. We must keep our citizens informed. Oftentimes that is achieved via one-way communication tool such as newsletters; however, we strive to partner with our citizens to achieve full public collaboration. “People have a tendency to agree with something they helped create.”
|
|